Sequence is the cheapest thing to get right and the most expensive to get wrong. Tick what applies and the order falls out, with the reasoning attached.

Before anything is touched
Opening up
Services, while the walls are open
Closing up
Finishes
Finishing off

This planner runs in your browser and needs JavaScript switched on. The full sequence, with the reason behind each step, is in the order of operations guide.

Why this is a planner and not a schedule

It gives you order, not dates. Durations depend on the size of the job, how many trades are working, what the weather is doing and what gets found behind the first wall that comes off. Anyone who gives you a confident timeline before demolition is guessing.

What is reliable is the dependency order, because it comes from physical constraints rather than from estimates. A pipe cannot go in after the wall. A screed cannot be dry before it has had its drying time. A floor cannot be undamaged if people are still carrying tools across it.

The three rules underneath the whole sequence

Buried before covered. Anything that ends up inside a wall, floor or ceiling goes in before that surface closes. Pipes, cables, ducts, insulation, and the timber backing for everything you will later screw to a wall.

Dirty before clean. Demolition, cutting, chasing, sanding and screeding all produce dust that gets everywhere and settles for weeks. They come before anything that has to end up clean — and far before the flooring.

Slow before fast. The things with long lead times or long drying times start early, even if they finish late. Order windows before you demolish. Pour screed with enough weeks left for it to dry. Apply for permits on day one.

The usual mistakes

Flooring too early. It is the finish people are most excited about and it should be one of the last things laid. Every trade after it will damage it.

Decorating before carpentry. Skirting, architrave and door linings all need filling and sanding. Paint first and you paint twice.

Deciding the kitchen layout after the first fix. Every socket, every isolator, every waste and supply position depends on where the units go. Change the layout afterwards and you are paying an electrician and a plumber to undo finished work.

Closing a wall without photographing it. Five minutes, with a tape measure in shot. The one piece of documentation you will certainly want later.

No contingency in the programme. Not just in the budget — in the timeline. Something will be found, delayed, or delivered damaged. A schedule with no slack converts a two-day problem into a three-week one, because every trade after it has to be rebooked.

Common questions

Why does the order matter so much?
Because some steps make others impossible. Anything inside a wall has to go in before the wall closes. Anything that makes dust has to happen before anything that must stay clean. A floor laid before the trades have finished is a floor that gets damaged. Getting the sequence wrong does not usually mean a worse result — it means paying twice for the same work.
Plumbing or electrics first?
Plumbing, where the two clash. Waste pipes need a continuous fall and cannot be rerouted around an obstruction; a cable can be routed around almost anything. So the pipes claim their line first and the electrician works around them.
What are the long-lead items?
Anything made to order. Windows, bespoke or imported kitchen units, stone worktops, specialist tile and some flooring commonly run six to twelve weeks. These get ordered at the start, before demolition, because a project waiting on a delivery is a project paying for an empty house.
Where do permits fit?
First, and in parallel with everything else. Applications take weeks and can come back with conditions that change the design. Start them on day one and let them run while you do the surveys and the drawings.