Why this checklist exists
Once a wall is boarded and skimmed, everything inside it is gone. Not inaccessible — gone, in the sense that reaching it means breaking a finished surface, patching it, and repainting the room.
Run this list the day before the boarding starts. It takes half an hour.
Services
- Every cable run complete, and terminated where it needs to be
- Every pipe run complete, and pressure tested where it can be
- Waste pipework with a continuous fall, checked with a level, not by eye
- Ducting complete, from the unit to where it terminates outside
- Socket and switch boxes in their final positions, at final heights
- Isolators and switched connections for every fixed appliance
- Task lighting positions and their switching settled, not just the ceiling light
- A spare conduit or draw cable left in, where it costs nothing to do now
Backing and fixings
Everything that will later be screwed to this wall needs something solid behind the board. Plasterboard fixings carry much less than timber, and the failures are the kind that take the plaster with them.
- Noggins for wall-hung cupboards and shelving
- Backing for a wall-hung basin or toilet frame
- Backing for a radiator or towel rail
- Backing for a shower screen and for any grab rail
- Backing for a wall-mounted television or extractor
- Backing for curtain or blind fixings, if the window reveal is being boarded
Insulation and sealing
- Insulation in, complete, with no gaps at the edges or around services
- No insulation compressed or stuffed, which stops it working
- Air sealing done at junctions and penetrations
- Acoustic insulation in any wall where sound matters — it is a one-time chance
- Fire-stopping where required, especially where services pass through
Structure and substrate
- Any structural work complete and, where required, inspected and signed off
- Nothing notched, drilled or cut through a joist or beam without approval
- Frame checked for plumb and level, and the face checked for flatness
- No damp, no rot, nothing damaged left inside the wall
- Any timber treated where it needed treating
The photographs
- Every wall photographed, straight on, before boarding
- A tape measure in shot in every picture, for scale
- Close-ups of anything unusual: a joist position, a pipe route, a junction
- Ceilings and floors photographed too
- Files saved somewhere that will still exist in ten years, and named by room
This is five minutes of work and the most useful documentation in the entire project. In two years, when you want to hang something heavy or you have a leak, these pictures are the only record of what is behind the plaster.
Last pass
- Walked the room with the drawing in hand, item by item
- Asked each trade directly: is there anything you still need to get to in here?
- Checked nothing has been left in the void — tools, offcuts, rubbish
- Signed off, in writing or by message, that boarding can begin