Decide these before anything comes out

The layout, finally. Every pipe, cable, waste and backing timber depends on it. Changing a basin position after first fix means opening a finished wall.

Where the water goes. Waste pipework needs a continuous fall to the stack, and there are limits on run length and gradient. This constrains the layout more than anything aesthetic, and it is the first question to put to a plumber.

What is behind the walls. In an older building, what the walls are made of decides what can be fixed to them and what the waterproofing system must be compatible with. If the building is from roughly 1930 to the 1990s, get an asbestos survey before demolition.

Ventilation. Capacity, where the duct runs, where it terminates. Usually a regulatory requirement, always the thing that decides whether your new bathroom has mould in three years.

Every fitting, chosen and ordered. Not "a basin like that one" — the actual model, because the waste position, the tap hole configuration and the fixing centres all differ, and the plumber needs them at first fix. Sanitaryware is also commonly on a long lead time.

Door clearance and floor build-up. A new floor is usually thicker than the old one. Check the door still opens.

The waterproofing is the job

Tile is not waterproof. Grout is not waterproof. Water passes through cement-based grout, and always has.

What keeps water out of the structure is a membrane or liquid-applied system behind the tile, installed as a continuous layer to a national standard, with properly formed joints at corners, at the floor-to-wall junction, and around every pipe penetration. In most countries this is specialist work with its own certification, it is frequently a condition of your home insurance, and it usually comes with a documented guarantee.

This matters because the failure is silent. A wet area that leaks does not leak visibly into the room. It wets the structure behind, for years, and presents as a stain on a ceiling below or a soft floor — at which point the entire room comes out again.

So: this is the line item not to shop on price, and the one to get paperwork for. Everything you can see in a bathroom can be replaced in ten years for a fraction of what it costs to redo what is behind it.

Electrics in a wet room

Bathroom electrics are more tightly regulated than anywhere else in a house, because water and electricity in the same small room is exactly the hazard the rules exist for. Most countries define zones based on distance from the bath or shower, and each zone restricts what may be installed and to what protection rating.

What that means practically: where a light, a shaver socket, a heated towel rail or an extract fan may go is not a free choice, and nor is the switching. Plan the positions you want and have a licensed electrician tell you which of them are possible.

The sequence, specifically

  1. Survey, if the building's age calls for it
  2. Final layout, every fitting selected and ordered
  3. Protection, and a dust wall at the door
  4. Strip out completely
  5. Any structural work
  6. Plumbing first fix — pipes before cables, because waste needs its fall
  7. Electrical first fix, to the zone rules
  8. Extract ventilation and ducting
  9. Backing timber and noggins for everything that will be fixed to a wall: basin, cistern frame, grab rails, towel rail, shower screen
  10. Boarding — and photograph every wall before it closes
  11. Waterproofing, to standard, signed off
  12. Screed or levelling, with its drying time respected
  13. Tiling, then grouting, with full cure times
  14. Decorating
  15. Second fix: sanitaryware, taps, shower, fittings
  16. Silicone sealing
  17. Testing, certificates, snagging

The small things that decide how it feels

Storage. The single most common regret. A bathroom with nowhere to put anything looks beautiful for a week.

Where the towel is. Within reach of the shower, without crossing wet floor.

Lighting in layers. One central light makes everyone look unwell. A light at the mirror, at face height rather than overhead, and something low for the night makes more difference than any fitting you can buy.

Threshold and drainage falls. A level-access shower needs the floor to fall towards the drain, which is a build-up and screed question settled long before tiling.

Silicone, not grout, at every change of plane. Internal corners, wall-to-floor, around the bath. Rigid grout in a joint that moves cracks, and that crack is a route for water.

Common questions

What is the most expensive bathroom mistake?
Waterproofing that fails. It is invisible for years and then presents as rot, a stained ceiling below, or a floor that has to come out entirely. Everything else in a bathroom can be changed later for a fraction of the cost of redoing a wet area.
Can I move the toilet?
Sometimes, and it depends on whether a waste pipe can reach the existing stack with a continuous fall. There is a limit to how far soil pipework can run and how shallow the fall can be, and it is a question for a plumber looking at your building rather than a design decision.
Do I need extra ventilation?
Almost certainly, and it is usually a regulatory requirement rather than a preference. A bathroom without effective extraction grows mould and damages the finishes you just paid for. The capacity needed depends on the room and on local rules.
How long does a bathroom take?
Longer than the working days suggest, because of waiting: waterproofing cure times, adhesive setting, grout curing, screed drying. A small bathroom with no structural work is commonly two to three weeks of elapsed time even where the labour is less.