The three rules
Learn these and you can work out the order for any project, including the parts no list covers.
Buried before covered. Pipes, cables, ducts, insulation and the timber backing for anything you will later screw to a wall all go in before the surface closes over them.
Dirty before clean. Demolition, chasing, cutting, sanding and screeding produce dust that travels through a whole house and settles for weeks. Everything that must end up clean comes after.
Slow before fast. Long lead times and long drying times start early even though they finish late. Permits, made-to-order items and screed all run on their own clock and ignore yours.
Phase 1 to 5: before anything is touched
Surveys and tests. Asbestos, lead paint, damp, electrical condition, structural condition. Findings here can change the entire plan, so they come before you spend money on design or materials. In a building from roughly 1930 to the 1990s, an asbestos survey before demolition is not optional caution — it is the difference between a normal job and a contaminated site.
Permits and approvals. Weeks, sometimes months, and they can come back with conditions that change the design. Start on day one and let them run.
Final drawings and decisions. Every later trade works from these. A kitchen layout settled after the first fix is a kitchen layout you pay for twice.
Order the long-lead items. Windows, bespoke units, stone worktops, specialist tile, much flooring: six to twelve weeks is normal. Before demolition, not after.
Protect and set up. Dust sheeting, floor protection, a dust wall across the doorway, skip or container, temporary kitchen, somewhere to wash. An hour here saves a week of cleaning, and a proper dust wall is the difference between one dusty room and a dusty house.
Phase 6 to 9: opening up
Strip out and demolition. Everything that is leaving, leaves now. Working around something you meant to remove is the most common self-inflicted delay in renovation.
Structural work. Openings, beams, anything load-bearing. Nothing else can be fixed in place until the building's shape is final. This needs an engineer's calculation and, in most places, approval before anything is cut.
Windows and external doors. They make the building weathertight, and plaster and flooring both need a dry, closed shell.
Roof and external envelope. Stop water getting in before spending money on anything inside. Obvious, routinely ignored.
Phase 10 to 13: services, while the walls are open
Plumbing first fix. Pipes before cables where the two clash. Waste pipes need a continuous fall and cannot detour around an obstruction; a cable can be routed around almost anything. So the pipes claim their line first.
Electrical first fix. Cables, back boxes, and the position of every switch, socket and light. This is the last moment the layout is free to change.
Heating and ventilation. Radiators, underfloor loops, ducting, extract routes. All of it is buried by the next phase.
Insulation and air sealing. Only possible while the structure is open. Skipping it here means never, or means doing the whole thing again.
Phase 14 to 16: closing up
Boarding and plastering. The point of no return. Everything behind the wall is now inaccessible. Photograph every wall before it closes, with a tape measure in shot. This is the five minutes you will thank yourself for.
Screed and floor levelling. Drying time is measured in weeks, not days, and it depends on thickness, temperature and ventilation. Lay flooring on a damp screed and the floor fails — not immediately, which is the problem.
Carpentry second fix. Door linings, skirting, architrave, stairs. Before painting, because all of it needs filling and sanding.
Phase 17 to 21: finishes
Kitchen installation. Units go in before the worktop is templated, because stone and solid-surface worktops are measured from the installed units, not from a drawing. In most layouts, units before flooring too.
Tiling. Wet areas need their waterproofing done and signed off first — the tile is not the waterproofing and never was. Tile before final paint.
Decorating. Mist coat on new plaster, then fill, sand, finish. Late enough that the mess is behind you, early enough to touch up afterwards.
Flooring. Near the end, so the trades are not walking on it. Wood and laminate need their acclimatisation days in the room first.
Electrical and plumbing second fix. Faceplates, light fittings, taps, sanitaryware, appliance connections. Fast, and it needs the finishes done.
Phase 22 to 24: finishing off
Testing and certification. Electrical certificate, gas safety check, pressure tests, building-control sign-off. Get the paperwork and keep it: it matters at resale and it matters to your insurer. A job without its certificates is not finished, whatever it looks like.
Snagging. Walk the job in daylight with a written list, before final payment. Raise everything while the trades are still on site and still want paying. There is a snagging checklist for this.
Deep clean and move back. Construction dust needs more than one pass. Filters, extract grilles and the tracks in window frames hold it for months.
When your project does not fit
It will not fit. Projects never do. Three worked examples of reasoning from the rules instead of the list.
A bathroom with no structural work. Skip structure, windows and roof. Everything else holds, and the waterproofing phase becomes the most important one in the job — it sits after boarding and before tiling, and it wants a documented guarantee.
Decorating only. Protection, then carpentry repairs and filling, then decorating, then flooring if it is included. The "dirty before clean" rule is the whole sequence here: all the sanding happens before any paint.
A kitchen in an older house. The services phases are where the risk is. Expect the first fix to find something, and have the contingency ready in both money and days. Order the units early, and do not let the layout change after the electrician has been.
Common questions
- Does every project follow this order?
- No project uses every phase, but the relative order holds, because it comes from physical dependencies rather than convention. Use the order planner to filter it down to your job, and when something does not fit, reason from the three rules rather than from the list.
- Can phases overlap?
- Many can, and on a larger job they must or it takes forever. What cannot overlap is anything where one phase makes another impossible — nothing goes inside a wall after it is boarded, and nothing clean happens while something dusty is still running.
- What if something is found during demolition?
- Stop and re-plan rather than pressing on. This is what the contingency in both the budget and the timeline is for. Rot, unexpected structure, a pipe where no pipe should be, or anything that looks like asbestos all change the plan, and the cheapest moment to change it is immediately.
- Where does tiling go relative to painting?
- Tiling first, painting after. Grout haze, cut dust and adhesive splashes all ruin fresh paint, and the final coat wants to come after the mess. The exception is a ceiling, which is usually painted before wall tiling starts.