Planning a kitchen renovation

A kitchen is a services project wearing a furniture project's clothes. Almost every decision you make about how it looks is constrained by something behind the units.

8 min read · Updated 2026-11-21

A kitchen with dark fluted cabinetry, warm timber shelving and a wooden breakfast bar.

The order the decisions constrain each other

Kitchen planning goes wrong when people decide in the wrong order. The sequence of decisions is as important as the sequence of work.

1. What the room can do. Where the drainage is and what fall is available. Where gas, if any, comes in. What the electrical supply can take — a modern kitchen may need more circuits than an older board can provide. Whether ventilation can be ducted to outside and where it terminates. Whether any wall you want to move is structural.

2. The layout. Now, with those constraints known. Where the sink, hob, oven, fridge and dishwasher go. Once this is fixed, almost everything else follows from it.

3. The appliances, specifically. Actual models, because dimensions, clearances, ventilation requirements and connection types all differ, and the cabinet sizes depend on them. An integrated appliance chosen after the units are ordered is a problem.

4. The units. Carcass sizes, door style, handles, internal fittings.

5. The worktop. Material decides thickness, support requirements, whether joints are visible and how the sink is mounted — and stone and solid surface are templated from the installed units, which puts them at the end of the programme no matter how early you choose them.

6. The finishes. Splashback, flooring, paint, lighting.

Work in that order and each decision narrows the next. Work backwards from a picture and you will find the drainage will not reach.

Where the money and time actually go

The visible parts — doors, handles, worktop — are what people shop for. The budget usually goes elsewhere:

And the time goes into waiting. Worktop templating and fabrication after the units are installed is commonly one to three weeks on its own, during which the kitchen is unusable.

Things to settle at first fix and never again

This is the last moment the walls are open. Everything here is cheap now.

Then photograph every wall before it is boarded, with a tape measure in shot.

Living through it

A kitchen renovation removes the room the household runs on. Plan for it explicitly rather than enduring it:

The sequence of work

  1. Final layout, appliances and units ordered
  2. Protection, dust wall, waste removal arranged
  3. Strip out
  4. Structural work, if any
  5. Plumbing first fix
  6. Electrical first fix
  7. Ventilation and ducting
  8. Backing timber and noggins
  9. Boarding and plastering — photograph the walls first
  10. Levelling the floor, if needed
  11. Decorating the ceiling and the upper walls
  12. Units installed and levelled
  13. Worktop templated, then fabricated, then fitted
  14. Splashback or tiling
  15. Flooring
  16. Second fix: appliances, taps, sink, lighting
  17. Sealing, final decorating touch-ups
  18. Testing, certificates, snagging

The gap between steps 13 and 14 is the one that surprises people. Build it into the plan rather than discovering it.

Common questions

What has the longest lead time in a kitchen?
Usually the worktop, because stone and solid-surface tops are templated from the installed units rather than from a drawing, so the clock does not start until the units are in. Bespoke or imported units, and some appliances, can also run six to twelve weeks. Order everything early.
Flooring before or after the units?
Usually units first, then flooring up to them, so the floor is not trapped under the units and is not damaged during the fit. Check your flooring's own instructions, because some floating systems want a continuous expansion gap and some must not run under fixed furniture.
How many sockets do I need?
More than the plan says, and in places you have not thought about: inside a cupboard for a charger, at the back of a worktop run for appliances that move, somewhere for a device on the counter. Adding one at first fix is almost free; adding one afterwards means chasing a finished wall.
Can I move the sink?
It depends on reaching a waste with a continuous fall, which is a plumbing constraint rather than a design choice. Moving a sink across a room is frequently possible and occasionally impossible, and the answer comes from someone looking at where the drainage runs.