How the figures are worked out
Rectangular pours. Length × width × depth × how many. Depth is entered in millimetres or inches because a slab is rarely a metre thick.
Post holes. π × (diameter ÷ 2)² × depth × how many. A hole is a cylinder, and treating it as a box overstates the concrete by about 21%.
Waste. Added to the total. Ten per cent is the usual allowance and it is mostly for over-dig: formwork that bellies, a subgrade that is not as flat as you thought, and the bit left in the mixer.
Bags. The volume divided by what one bag yields. The default is 11 litres for a 25 kg bag, or 0.6 cubic feet for an 80 lb bag — both are typical, both vary by brand, and the figure is printed on the bag.
Mixing from raw materials. At 1:2:3 cement to sharp sand to aggregate by volume, the dry materials come to about 1.55 times the finished volume. The cement figure is converted to weight at 1440 kg per cubic metre.
What this calculator does not cover
It gives you volume, not a specification. Concrete strength, the aggregate size, the water-cement ratio, whether the mix needs air entrainment for frost, how much reinforcement goes in and where it sits in the depth — all of that is specification, and all of it matters more than the volume does.
For anything that holds a building up, that specification comes from an engineer and usually has to satisfy a building control inspection. Footings, retaining walls, a slab under a load-bearing wall, anything near a drain or a boundary: get the design before you get the quantity.
The parts people get wrong
Measuring the hole you want, not the hole you dug. Hand-dug holes are always wider at the top and rarely plumb. If you dug it with a spade rather than an auger, measure what is actually there.
Forgetting the thickening. Many slabs are not a constant depth — they thicken at the edges or under an internal wall. Add those as separate rows rather than averaging them in your head.
Ordering ready-mix short. A part load has a minimum charge, and the gap between 1.4 and 1.5 cubic metres usually costs nothing. Running out at ninety per cent costs you the whole pour.
Not having enough hands. Concrete does not wait. Before the truck arrives you want the formwork braced, the route planned, the tools wet, and more people than you think you need.
Common questions
- How many bags of concrete make a cubic metre?
- Around 90 bags of 25 kg ready-to-mix, because one bag makes about 11 litres of finished concrete. That is a lot of mixing by hand, which is why a cubic metre is roughly the point where a ready-mix part load becomes cheaper as well as easier. Check the yield printed on the bag you are actually buying — it varies more between brands than people expect.
- Why is the dry material more than the finished volume?
- Because the cement paste fills the air gaps between the stones rather than adding to them. The standard allowance is about 1.55 times: to end up with a cubic metre of concrete you start with roughly 1.55 cubic metres of dry cement, sand and aggregate.
- What depth should a slab be?
- It depends entirely on what goes on top and what is underneath, which is why this calculator asks you for the depth rather than suggesting one. A garden shed base, a driveway that takes a car and a footing under a load-bearing wall are three different numbers, and the last one is a structural question for an engineer, not a website.
- Can I pour in two sessions?
- Not within the same element. Where one batch has started to go off before the next arrives you get a cold joint, which is a permanent plane of weakness and the usual reason a slab poured over two afternoons cracks in a suspiciously straight line. Separate bays with a proper joint are fine; a stop halfway across one bay is not.