Board width plus the gap is what actually covers the deck, so that is what this counts. It gives you linear run first and whole boards second.

The deck
Boards and frame

This calculator runs in your browser and needs JavaScript switched on. The method is written out under How the figures are worked out.

How the figures are worked out

Deck area. Length × width × how many, added up over every section.

Board run. A row of decking covers its own width plus one gap, so the run is the area divided by (board width + gap). That is the figure that matters when you are ordering: it is real linear metres of board.

Boards. The run plus waste, divided by the board length, rounded up. Waste is higher on decking than on most materials because every board that does not reach the far side leaves an offcut you cannot use at the same end.

Joist timber. Area divided by the joist centres. That is close enough to order from, and the calculator says so — it is an approximation that does not know the shape of your deck.

Frame perimeter. Twice the length plus the width of each section, listed separately because the outer frame is usually a heavier section than the intermediate joists.

Screws. Two per board at every joist crossing, rounded up to the nearest 50.

What the calculator cannot tell you

It sizes the material, not the structure. Joist depth, post size, footing depth, how the deck is fixed to the house and whether it needs fixing to the house at all — those come from the span, the height off the ground, and what your local rules say about decks over a certain height or area.

A raised deck is a structure that people stand on in groups. The failures are not the boards; they are the ledger fixing into the house and the posts into the ground.

The order things go in

The frame is set out, levelled and fixed before a single board is cut. Fall is built into the frame, not the boards — a deck wants a slight slope away from the building so water leaves rather than sits.

Leave air underneath. A deck laid straight onto soil or trapped against a wall has no way to dry out, and the boards rot from the side you cannot see. The timber will also want the end grain of every cut sealed, which is the step everyone skips and the place rot always starts.

Common questions

How big should the gap between boards be?
Usually 5 to 6 mm, about a quarter of an inch, but it depends on how wet the timber is when you lay it. Softwood that arrives soaking from the yard is already at its widest and will shrink, so gap it tighter. Kiln-dried board laid in summer will swell, so give it the full gap. A deck laid tight in August is a deck that buckles in November.
What spacing do the joists need?
400 mm (16 in) suits most softwood decking at the usual thicknesses, and some thinner or composite boards want 300 mm or less. It is set by the board, not by convention, so check what the manufacturer specifies — too far apart and the deck feels bouncy underfoot, which is impossible to fix afterwards without lifting everything.
Should boards run along the deck or across it?
Across the joists, always — that is structural. Which direction that puts them in is up to you, and the usual choices are running away from the house to lead the eye out, or running along the longest sight line so there are fewer end joints. A diagonal layout looks good and costs about 15% more in boards.
What screws should I use?
Stainless steel, or a coated decking screw rated for exterior use. Plain steel bleeds rust stains down the face of the board within a season, and in oak or cedar the tannins eat it. Two per board at every joist crossing is the normal rate.